top of page
Search
  • Jodie Alexander

From the DOE Loan Programs Office: 10 Questions to Ask Before Applying to LPO

This post condenses info from an article the Director of the LPO posted in December. To view the full article, click here.




The Department of Energy’s (DOE) Loan Programs Office (LPO) provides access to debt capital for high-impact energy and manufacturing projects. Over more than a decade, LPO has developed a strong understanding of what makes a project more likely to advance through LPO’s processes, as well as the areas that commonly slow down or stop projects in the process. The following tips suggest best practices for considering whether LPO financing could be the right choice and what to include or what to avoid when applying to work with LPO.


Financial

1 - Is our project big enough, and how much debt financing is typical for a project?  

Due to the way that LPO programs are funded, there are expenses associated with obtaining an LPO loan that average several million per application. While there is no statutory lower limit on the size of a loan that LPO can provide, they become less attractive for borrowers under ~$100 million. For reference, the average loan requests at LPO are nearly $1 billion, and the smallest loan requests are around $100 million.


2 - Do we have a reasonable strategy for selling what we will be producing?

While LPO can underwrite some level of merchant risk, the nature of project financing is that certainty of project cash flows is optimal.  Every LPO loan must have a reasonable prospect of repayment, which is largely determined by the certainty and quality of payments from customers and generally need to be obtained prior to a loan being issued. Ideally, LPO looks for signed offtake contracts or committed letters of intent for a significant portion of each project. Sometimes, loan tenors can be longer than the length of offtake contracts. 


3 - Have we raised development capital, and do we have committed project equity?

The various elements of developing a commercial-scale energy infrastructure or manufacturing project—such as pre-FEED (front-end engineering and design) studies, Front-end Loading (FEL)-2’s, permitting, analyses, financial advisors, and legal counsel—all require significant capital. Successful applicants have this capital in place when they begin the application process, and they almost always have several of these pieces in place.


While LPO can lend up to 80% of eligible project costs by statute, a 50–70% loan-to-value is more typical in the office’s portfolio. Applicants should expect to have 30–50% of their total capital needs met with equity dollars that are committed at the project level, and they will need to show early in the application process that they have this equity in place or have a clear path to obtaining it.


Technical and Environmental

4 - Do we need a successful demonstration or pilot for our project?

One of the unique values that LPO offers is its team of engineers, backed by the scientific expertise across DOE and the National Labs. When considering an Innovative Energy or Innovative Supply Chain project under the Title 17 Clean Energy Financing Project, LPO’s engineers generally look for 1,000–2,000 hours of demonstration or pilot plant operations that successfully prove the technology being commercialized will work as intended and designed. LPO also likes to see at least one, but preferably two or more, operations & maintenance cycles to demonstrate that the prospective borrower understands what it will take to maintain the facility/process being financed.


LPO also offers loan products for projects that use already commercially-deployed technologies—State Energy Financing Institution projects, Energy Infrastructure Reinvestment projects, ATVM projects, and Tribal Energy projects. LPO will evaluate the project’s technology in due diligence similarly to how a private lender would.


5 - Has our project been designed and engineered, and is it commercially ready for construction and operations?

Most successful applicants begin the application process with a completed FEED or pre-FEED study.  During due diligence, LPO will contract an independent engineering firm (paid for by the applicant) to produce an Owner’s Engineer Report to independently assess the project and identify technical risks that could impact loan repayment. LPO will also look for signed engineering, procurement, and construction (EPC) contracts to demonstrate that the project is feasible and ready to be built.  LPO looks favorably upon full-wrap EPC contracts and will evaluate the capabilities of the applicant and its EPC contractors to construct and start up the project during application review.


Projects are typically Technology Readiness Level 8 and above.


6 - What level of environmental review do we need?

The scope of an applicant’s project determines the extent of the environmental review pursuant to National Environmental Policy Act (NEPA) and the associated regulatory agency consultations that are required of federal agencies (e.g., reviews and consultations pursuant to the Endangered Species Act and the National Historic Preservation Act).


The NEPA process is a forward-looking process that allows federal agencies to study the environmental effects of the applicant’s proposed actions (activities associated with construction, operation and, in some cases, decommissioning) and reasonable alternatives. Therefore, an applicant should factor in time in its anticipated construction schedule to allow LPO, in coordination with the applicant, to complete the NEPA review process prior to the start of construction—this could include a request for LPO to start the NEPA early in the process. This sounds complicated but LPO can help you through it—just ask.


7 - Do we have site control and necessary regulatory approvals?

Successful applicants own their project site or have signed a lease agreement that gives them full control of their site. They have also obtained (or are in the process of obtaining) all necessary federal, state, and local permits and authorizations to site, construct, operate the project, and, if necessary, to connect to the electric grid.


Prospective applicants can engage in pre-application consultations prior to obtaining site control and all permits; however, the most productive conversations occur when the prospective applicants can describe its status in identifying and securing a site and its permits, as well as the required zoning designation to operate. Having the necessary regulatory approvals to show your project is ready to build demonstrates commercial readiness.


8 - Do we have an experienced management team that has successfully built projects before?

A quality and experienced management team lowers the risk of a project because leaders have the capability to solve the inevitable challenges that arise when building large, innovative energy projects. LPO looks strongly upon management teams that have experience in developing, financing, and executing large infrastructure projects.


Community and Climate Benefits

9 - Can we demonstrate the emissions benefits of the project? 

Every project receiving Title 17 financing must achieve significant and credible greenhouse gas (GHG) and/or air pollution avoidance, reduction, utilization, or sequestration. Successful applicants may provide data to LPO demonstrating their emissions benefit relative to a business-as-usual case. LPO’s Technical and Environmental Division will perform a full life cycle analysis of the project in the Part I application review to determine project eligibility. Projects that have already run an analysis may submit this data as ancillary information, but the GHG analysis performed by LPO is the final and only determination for Title 17 eligibility.


10 - Have we considered how the project will benefit the local community?

Successful applicants for any of LPO’s programs must submit a Community Benefits Plan (CBP) that explains how the proposed project will support (a) community and labor engagement; (b) quality jobs; (c) diversity, equity, inclusion, and accessibility; and (d) environmental justice (as addressed through the Biden-Harris Administration’s Justice40 Initiative).


Developing a CBP is a recognition that choosing a community is a multi-decade commitment to a positive impact on the lives of a project’s community members. Collaborating with partners, such as local governments and labor unions, can help build institutional support and secure a skilled, high-quality workforce throughout the life of a project. 






Grant Management Associates has years of experience with opportunities like these. Contact us today for a consultation.

24 views0 comments

Recent Posts

See All
bottom of page